I am finding impossible in Ptoject 2000 to specify a one off working time for a resource. e.g. 4 hrs on 26 April 2004. No cycle. I have tried making the entire resource calander non- working time first but that is prevented. I have tried making each day at a time non-working without success. I must be missing something simple? |
|
#2
|
|||
|
|||
|
Resource Information, Resource Availability, From, To
HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional [url]http://users.online.be/prom-ade/index.htm[/url] 32-495-300 620 "Michael Waite" <anonymous@discussions.microsoft.com> schreef in bericht news:337d01c4292b$3baa3700$a401280a@phx.gbl... > hi, > I am finding impossible in Ptoject 2000 to specify a one > off working time for a resource. e.g. 4 hrs on 26 April > 2004. No cycle. > I have tried making the entire resource calander non- > working time first but that is prevented. I have tried > making each day at a time non-working without success. > > > > I must be missing something simple? |
![]() |
| Bookmarks |
| Thread Tools | Search this Thread |
| Rate This Thread | |
|
|